City of Cuyahoga Falls Service Director Anthony Zumbo announced that the second phase of the Triangle Project at State Road, Seasons Road, and Wyoga Lake Road is scheduled to begin on November 25.
During this phase, the contractor will begin installing new storm sewers in anticipation of the new roadway. This phase is anticipated to be completed by the end of 2024. Traffic will be maintained.
Work will then be suspended until the spring of 2025, at which time major roadway work will begin. During this phase, State Road will be reduced to one lane southbound between Hidden Lakes Lane and Boulder Boulevard. Detour signs will direct northbound drivers to use East Steels Corners Road and Wyoga Lake Road to continue north on State Road. All work is scheduled to be completed by the fall of 2025.